Subproject by Stage as of February 22, 2017

Stages of Subprojects Number of
Subprojects
Subproject Cost
LP GEF GOP LGU Equity Total
Approved Subprojects452492,353,566.256,729,840164,117,855.42165,800,315.42829,001,577.08
Completed (100%)84,800,00001,600,0001,600,0008,000,000
Restoration / RehabilitationProponent Groups  (8)
Members  (2,766)
84,800,00001,600,0001,600,0008,000,000
Under Implementation1962,746,086.94020,915,362.3120,915,362.31104,576,811.56
Fifty percent and above progress618,674,443.2006,224,814.406,224,814.4031,124,072
Upgrading / ExpansionProponent Groups  (5)
Members  (250)
116,857,00005,619,0005,619,00028,095,000
Restoration / RehabilitationProponent Groups  (5)
Members  (219)
51,817,443.200605,814.40605,814.403,029,072
Less than fifty percent progress916,860,393.3505,620,131.115,620,131.1128,100,655.58
Start-upProponent Groups  (4)
Members  (553)
29,417,795.5203,139,265.173,139,265.1715,696,325.86
Upgrading / ExpansionProponent Groups  (22)
Members  (1,660)
14,372,20001,457,4001,457,4007,287,000
Restoration / RehabilitationProponent Groups  (6)
Members  (2,370)
63,070,397.8301,023,465.941,023,465.945,117,329.72
With NOL 2427,211,250.3909,070,416.809,070,416.8045,352,083.98
Start-upProponent Group  (1)
Members  (50)
1890,657.430296,885.81296,885.811,484,429.05
Upgrading / ExpansionProponent Groups  (5)
Members  (2,634)
225,720,592.9608,573,530.998,573,530.9942,867,654.93
Restoration / RehabilitationProponent Group  (1)
Members  (198)
1600,0000200,000200,0001,000,000
Under Procurement425424,807,479.316,729,840141,602,493.11143,284,953.11716,424,765.52
With NOL 1425424,807,479.316,729,840141,602,493.11143,284,953.11716,424,765.52
Start-upProponent Groups  (54)
Members  (17,173)
23113,034,074.81037,678,024.9437,678,024.94188,390,124.68
Upgrading / ExpansionProponent Groups  (84)
Members  (17,543)
1793,829,906.35031,276,635.4531,276,635.45156,383,177.24
Restoration / RehabilitationProponent Groups  (398)
Members  (45,362)
381217,943,498.15072,647,832.7272,647,832.72363,239,163.60
Global Environmental Facility (GEF)Proponent Groups  (6)
Members  (286)
406,729,84001,682,4608,412,300
Pipelined Subprojects151374,854,726.1920,806,252.61124,951,575.41130,153,138.56650,765,692.76
Endorsed for Issuance of NOL 135108,798,574.087,080,58436,266,191.3638,036,337.36190,181,686.80
Start-upProponent Groups  (23)
Members  (2,669)
1056,725,664.96018,908,554.9918,908,554.9994,542,774.94
Upgrading / ExpansionProponent Groups  (37)
Members  (3,566)
947,345,406.76015,781,802.2515,781,802.2578,909,011.26
Restoration / RehabilitationProponent Groups  (6)
Members  (199)
84,727,502.3601,575,834.121,575,834.127,879,170.60
Global Environmental Facility (GEF)Proponent Groups  (8)
Members  (368)
807,080,58401,770,1468,850,730
Approved by RPAB93187,487,734.735,887,589.8962,495,911.5963,967,809.06319,839,045.27
Start-upProponent Groups  (11)
Members  (2,327)
1081,032,102.88027,010,700.9627,010,700.96135,053,504.80
Upgrading / ExpansionProponent Groups  (27)
Members  (1,765)
1067,424,365.41022,474,788.4722,474,788.47112,373,942.35
Restoration / RehabilitationProponent Groups  (29)
Members  (722)
6839,031,266.44013,010,422.1613,010,422.1665,052,110.76
Global Environmental Facility (GEF)Proponent Groups  (4)
Members  (193)
505,887,589.8901,471,897.477,359,487.36
Business Plan Preparation2378,568,417.387,838,078.7226,189,472.4628,148,992.14140,744,960.69
Start-upProponent Groups  (8)
Members  (1,477)
1348,700,706.98016,233,568.9916,233,568.9981,167,844.96
Upgrading / ExpansionProponent Group  (1)528,942,078.4009,647,359.479,647,359.4748,236,797.33
Restoration / Rehabilitation1925,6320308,544308,5441,542,720
Global Environmental Facility (GEF)Proponent Groups  (3)
Members  (362)
407,838,078.7201,959,519.689,797,598.40
Total603867,208,292.4427,536,092.61289,069,430.83295,953,453.981,479,767,269.86
Status Scope
Completed (100%) Covers subprojects with 100% physical progress (validated by the RPCOs / PSOs, with Joint Inpsection Team Inspection Report).
Less than fifty percent progress Covers subprojects that are (i) issued with Notice to Proceed (NTP) and (ii) undergoring construction activities (execution of contract) with physical progress below 50%.
Fifty percent and above progress Covers subprojects that are undergoring construction activities (execution of contract) with physical progress ranging from 50% to 99%.
With NOL 1 Covers subprojects issued with No Objection Letter (NOL) 1 allowing the proponent LGUs to proceed with procurement process.
With NOL 2 Covers subprojects issued with No Objection Letter (NOL) 2 allowing the proponent LGUs to proceed with awarding of contracts to the winning bidders.
Endorsed for Issuance of NOL 1 Covers subprojects under review by the PSO / NPCO for issuance of NOL 1
Approved by RPAB (for submission to the PSO for review / endorsement to the NPCO for NOL 1) Covers subprojects already approved by the RPAB that are (i) undergoing compliance with the conditions required by the RPAB prior to endorsement for NOL 1; and (ii) ready for endorsement to the PSO for review / endorsement to the NPCO for NOL 1.
Business Plan Preparation Covers subprojects that are (i) undergoing preparation of feasibility studies (FS), detailed engineering designs (DED), bidding documents and others required for approval; (ii) with draft FS (including DED, bidding documents, safeguards compliance documents, etc.) being reviewed by the RPCOs / PSOs prior to review / approval by the Regional Project Advisory Boards (RPAB); and (iii) For review / under review by the RPCOs, PSOs and NPCO for issuance of No Objection Letter (NOL) 1